SW 82 Avenue Roadway Improvements Project
Project Type:
Street
Project Status:
Approved
Date Received:
Friday, July 16, 2021
Location:
SW 82nd Avenue
See map: Google Maps
Location:
Project limits are along SW 82nd Avenue from SW 184 Street to Old Cutler Road.
Estimated Start:
Pending
Summary:
- Installation of a roundabout at SW 82 Avenue and SW 188 Street
- Drainage improvements at the roundabout
- New concrete sidewalks
- Installation of ADA ramps
- Curbs and gutter
- Milling and resurfacing of entire SW 82 Ave corridor
- Fill in gaps in the sidewalk along the west side of SW 82 Ave
- New pavement markings and signage, throughout project
- New bicycle share lane (bike sharrows)
- Landscaping of roundabout
Funding:
- Grant from TPO - 2021 Transportation Alternatives Project for $800,000
- The Town will be matching $ 152,000 from municipal PTP Transportation Fund
Additional Information:
For additional information regarding this project, please call our Public Works Director, Alfredo Quintero, at (305) 234-4262 or email aquintero@cutlerbay-fl.gov.